Site Diary: What to Record, and Why It Arrives on Friday

Construction

It is Friday afternoon. The site manager sits in the cabin with a coffee and a blank site diary page for Monday, and tries to remember who was on site, what was delivered, what the weather did on Tuesday and when the excavator broke down.

Nobody plans it this way. The diary is a form, the form is on paper or in a spreadsheet on the office computer, and the site manager is outside doing the job all day. So it waits, and on Friday it gets written from memory. Some weeks it does not get written at all.

Why it matters more than it looks

Most of the time nobody reads the diary. Then something goes wrong, and it is the first document everyone asks for.

A diary written on Friday from memory is weak evidence in all three. An entry made on the day, with a time and a photo, is hard to argue with.

What a site diary should record

There is no statutory form, and the contract decides what records the client can ask for. Commentary published by NEC describes site diaries "which record daily resource expenditure, progress, stoppages and reasons for the stoppages against each activity performed" as indispensable for showing cause and effect (NEC). Under the NEC Engineering and Construction Contract, a compensation event not notified within eight weeks of the contractor becoming aware of it can be lost, so the diary is also where the clock starts.

For each job, each day:

What gets in the way

It is rarely the people. Site managers know the diary matters. The problem is the form.

What a same day diary looks like

The version I build runs on the phone the site manager already carries, inside the firm's own Microsoft 365.

  1. One screen, a few taps. The job is picked from a list. Labour, plant and deliveries are counts or picks, not paragraphs. Notes are optional.
  2. Photos instead of descriptions. A photo of the delivery ticket, the flooded trench or the scaffold handover says more than a sentence, and it carries its own date and time.
  3. Weather filled in. The day's weather for the site can be added automatically, so nobody has to remember Tuesday.
  4. Filed where the job lives. Each entry is saved under the job in SharePoint with its photos, so the office and the director see it the same day.
  5. A reminder when it is missing. If a live job has no entry by the end of the day, the site manager gets a message, and the office sees which jobs are behind.
  6. A PDF when someone asks. A week or a month of entries comes out as one document for the client, the QS or the solicitor.

What it costs to run

In most firms, nothing new. Power Apps, Power Automate and SharePoint come with the Microsoft 365 business plans most contractors already have, and site managers sign in with the account they use for email.

The work is in fitting it to the firm: its jobs, the fields that matter to it, and the people who need to see each entry. You pay for building it, not a monthly subscription per user.

Where to start

Pick one job and one site manager who will try it for a fortnight. Keep the form short: date, job, labour, plant, deliveries, weather, photos, notes. Add a field only when someone asks for it. After two weeks, put the new entries next to the ones written on a Friday and compare.

If you would rather start on paper or in Excel, the free site diary template has the same fields, one row per job per day, and the daywork sheet template covers the days that turn into a claim.

If the diary on your jobs gets written at the end of the week, or not at all, tell me what it looks like now. Half an hour on Teams, no charge, and I will tell you what I would build first and roughly what it would take.

Share:
Read next

Approvals in Power Automate for a Small Firm: Invoices and Purchase Orders

Read article

Something here sounds familiar?

Half an hour on Teams, no charge. You describe the process that eats your week, and I tell you what I would build first and roughly what it would take.